|
Case Study: HAECO Base Maintenance Hangar, Hong Kong
This contract was finished on the scheduled date 30th June
1998 at a total cost of £10 million, on behalf of Hong Kong Aircraft Engineering
Co. Ltd. The HAECO Base Maintenance Hangar is a 3 bay hangar, capable
of accommodating 3 no. wide body 747 jumbo jets fully under cover.
The hangar was designed by Meinhardt C & S Ltd. and consists
of a four storey concrete structure housing offices and workshops, with
a 70m cantilever roof, approximately 210m wide, covering the open hangar
area. The roof is supported by pinned connections to concrete shear walls
and 6 no. box section steel masts and stays.
HAECO Hangar Roof During
Construction
|
The Main Contractor for the project was Dragages et Travaux Publics
(HK) Ltd Cleveland Bridge were responsible for the connection design
and the supply, fabrication and erection of the 3,400t roof and gables.
This included door header steel and crane and gantry runway support
beams.
Cleveland were also subsequently awarded the assembly and erection
of the hangar doors. In order to accommodate the tight tolerances
required at the runway beams and door header steel, Cleveland engineered
an erection scheme that allowed the assembly of the roof to be carried
out at ground level. The roof was then strand jacked into position
in two separate lifts, each of approximately 1000t and connected
to the permanent pins and stays. Each strand jacking operation involved
lifting with nine hydraulically linked 180t jacks.
|
|